We'll be staying at HSH soon and got a welcome email that also included the following info about renovations to be done next summer.
It is with great excitement that I would like to inform you that in our continued effort to maintain and enhance our resort, we scheduled our very anticipated bathroom renovation to begin Summer 2018 during weeks 22-38. Each building will be shut down for a total of four weeks, please see schedule below:
• Building 1: June 3rd_ July 1st (weeks 22 -25)
• Building 2: July 1st_ July 29th (weeks 26-29)
• Building 3&4: July 29th -August 26th (weeks 30-33)
• Building 5: August 26th - September 30th (weeks 34-38)
The email goes on to say the pool and pool deck will also be out of service during weeks 22-27 in 2018 due to renovations.
Obviously this is going to mean a shortage of available units during weeks 22-38. I wonder if they will individually contact those who will be affected. We visit in the summer every year, but according to the schedule above, our building will be open during our week (though the pool will not be).
I can ask about this while we're at HSH but was curious to see if anyone else has more info.
It is with great excitement that I would like to inform you that in our continued effort to maintain and enhance our resort, we scheduled our very anticipated bathroom renovation to begin Summer 2018 during weeks 22-38. Each building will be shut down for a total of four weeks, please see schedule below:
• Building 1: June 3rd_ July 1st (weeks 22 -25)
• Building 2: July 1st_ July 29th (weeks 26-29)
• Building 3&4: July 29th -August 26th (weeks 30-33)
• Building 5: August 26th - September 30th (weeks 34-38)
The email goes on to say the pool and pool deck will also be out of service during weeks 22-27 in 2018 due to renovations.
Obviously this is going to mean a shortage of available units during weeks 22-38. I wonder if they will individually contact those who will be affected. We visit in the summer every year, but according to the schedule above, our building will be open during our week (though the pool will not be).
I can ask about this while we're at HSH but was curious to see if anyone else has more info.
Last edited: