Aloha and greetings from Marriott's Ko Olina Beach Club.
We are very excited to launch our villa renovation project for Hale Kona. This project includes a fresh new modern design incorporating the unique elements of our island culture in color scheme, pattern, and artwork. The project includes a full refurbishment of the villa and interior corridors including new furniture, kitchen & bath fixtures, kitchen appliances, light fixtures, artwork, drapery, window treatments, ceiling fans, carpet, kitchen flooring and paint.
Dates of Renovation: August 2, 2014 - October 18, 2014
Daily Hours of Work: 8:00 a.m. - 5:00 p.m.
Scheduled Floors:
Floor 12: August 2 - August 16
Floor 11: August 9 - August 23
Floor 10: August 16 - August 30
Floor 9: August 23 - September 6
Floor 8: August 30 - September 13
Floor 7: September 6 - September 20
Floor 6: September 13 - September 27
Floor 5: September 20 - October 4
Floor 4: September 27 - October 11
Floor 3: October 4 - October 18
Kona Lobby: September 25 - October 5
We sincerely appreciate your patience and understanding. We look forward to our fresh new look!
Mahalo,
Your Pre Arrival Team