The decking installation started last week, however combine a lost work day due to rain with a small work crew (varied from 2 to 4), not a lot of decking was installed. The two walkways/ramps from the gazebos to the hot tub are complete, but only 10% of the decking around the hot tub is complete.
The concrete cap for the fire pit bench and the fire pit itself was poured on Thursday - the concrete floor and curbs for the shower was poured on Friday.
At the current pace, April appears to be a more realistic completion date.